Drive Systems Goldstone WSW. 2 No. Replacement 132kW VSD cabinets & MCC Modifications

Goldstone WSW. 2 No. Replacement 132kW VSD cabinets & MCC Modifications

Goldstone WSW. 2 No. Replacement 132kW VSD cabinets & MCC Modifications

Scope of works

To design, manufacture, install and commission two new replacement 132kW drive sections using the ABB ACS800 low harmonic variable speed drive.

The contract consisted of the following:

  • 2 No. 132kW VSD cabinets.
  • 2 No. replacement control back plates, fitted into the existing MCC.
  • Software integration.
  • Site installation and commissioning.

The control for the drive was split into two locations due to a constraint imposed on the size of the kiosk which houses the two, 132kW VSD’s.

Southern Water


TSE is Southern Water's Standard Asset Supplier.

Client
Southern Water
Contract
Goldstone WSW. 2 No. Replacement 132kW VSD cabinets & MCC Modifications